Introduction
Column 37 which appeared last week dealt with the classification of costs and as indicated there, attention now turns to what Annex C describes as Pre-contract costs. In this regard, a major insertion in the 2016 Agreement which has aroused considerable curiosity relates to an amount of US$460,237,918 by the Contractors for pre-Contract costs incurred under the 1999 Agreement. This is included in section 3.1 of Annex C “Costs Recoverable Without Further Approval of the Minister”. This is also not the entire sum for pre-contract cost but represents only those costs claimed to have been incurred up to December 31, 2015. Additionally, the 2016 Agreement also provides that cost incurred between January 1, 2016 and the Effective date of the Agreement constitute part of the cost of petroleum operations. All that was required in the latter case was for the Contractor to notify the Minister of those costs no later than October 31, 2016. The Minister had six months to agree such costs.
The separation of the two costs suggests that the US$460,237,918 is final while in the case of the costs incurred between January 1, 2016 and the effective date, the time for any challenge was April 30, 2017. Continue reading “Every Man, Woman and Child in Guyana Must Become Oil-Minded (Part 38)”